TL;DR — Direct answer: A motor and generator factory needs clean, dry air at 6 to 7 bar for lamination stamping, winding, varnish impregnation, rotor balancing, assembly and test benches, with a pressure dew point of 3 degrees C and filtration to 0.01 micron so no oil or moisture reaches a winding, a varnish bath or a test bench. Size on the coincident peak of stamping and winding, 4 to 10 cubic metres per minute for a mid-size plant, roughly a 30 to 75 kW screw compressor with a variable speed drive. QiAir, a Chinese screw compressor manufacturer and supplier, builds fixed and variable speed machines with dry-air treatment for motor and generator factories.
A motor or a generator is a stack of precise electrical parts that must run for decades without failing. Silicon steel is stamped into laminations, copper wire is wound into stators and rotors, windings are impregnated with varnish under vacuum, rotors are balanced, and finished machines are tested for insulation, vibration and load before they leave the factory. Compressed air drives the stamping presses, feeds the winding machines, powers the vacuum pressure impregnation plant, blows windings clean and runs the test benches. A puff of oil on a winding weakens the insulation, moisture in a varnish bath changes the cure, and a pressure dip at the balancing machine changes the reading. The air system is part of the electrical quality, not just a utility. QiAir is a Chinese manufacturer and supplier of screw air compressors, and its machines for motor plants are specified around dry, clean air first and flow second.

The mistake buyers make most often is sizing air on the stamping shop alone and forgetting winding and impregnation. Stamping runs in bursts, winding is steady, the VPI plant draws air for its vacuum and pressure cycles, and the test area draws air for clamps and load banks all day. Add them together at peak and the real demand is typically 20 to 30 percent higher than the first estimate. This guide maps where the air goes in a motor and generator factory, explains how to size for stamping and winding peaks, sets the dry-air standard that protects windings and varnish, and shows what to put on a sizing sheet for a China supplier.
Where Air Is Used: Lamination Stamping, Winding, VPI and Balancing
Lamination stamping is the heaviest user. High-speed presses stamp silicon steel laminations, using air for press clamping, feed control, die cooling and scrap handling, and the demand pulses with every stroke. A stamping shop with four to twelve presses sees those pulses add up at the header, and the peak lands when several presses run together at full speed. Keep the pressure at the press within a narrow band, because a dip at the feed changes the strip position and produces a run of scrap laminations that will never stack true.
Winding, VPI, balancing and testing take the rest of the air and set the quality standard. Winding machines use it for wire tension control, coil insertion and taping, the VPI plant uses it for vacuum and pressure cycles and valve actuation, balancing machines use it for clamping and drive control, and test benches use it for clamping, load banks and cooling. The VPI plant is the most sensitive user: the air that drives its valves and purges its tanks must be dry, because moisture in the varnish changes the cure and weakens the insulation. A plant that maps every user, including the cleaning lances used between winding jobs, usually finds 15 to 25 percent more demand than the original estimate.
- Lamination stamping: press clamping, feed control, die cooling and scrap handling pulsing with every stroke.
- Winding and VPI: wire tension control, coil insertion, vacuum and pressure cycles that need dry air.
- Balancing and testing: clamping, drive control, load banks and cooling across the test area.
Sizing for Stamping Bursts and Winding Demand
List every line with its flow at peak and at steady running, because the two differ sharply in motor work. A mid-size plant with four to twelve stamping presses, six to twenty winding machines, a VPI plant and two to four test benches typically peaks at 4 to 10 cubic metres per minute at 6 to 7 bar, which is roughly a 30 to 75 kW screw compressor, and the peak usually lands when stamping and winding run together and the VPI plant is cycling. A variable speed drive earns its keep here: it follows the burst pattern of the presses instead of loading and unloading a fixed-speed machine dozens of times a shift, and it holds pressure within the narrow band that winding and balancing prefer.
Keep the pressure drop to the farthest winding machine under 0.3 bar at peak flow, and fit a receiver of 500 to 1000 litres per 10 cubic metres per minute to absorb press and VPI spikes. A ring main helps when the stamping hall, winding shop and VPI area sit in different parts of the building. Log pressure at the farthest test bench during a full production run for a week, because that log is the honest record of whether the compressor is big enough, and it settles arguments faster than any catalogue figure. Never raise the set point to mask a sag: every extra bar adds roughly 7 percent to power use and hides the real fault, which is usually a clogged filter or an undersized pipe.
- Size on the coincident peak of stamping, winding and VPI cycling, not on steady-state average flow.
- Use a variable speed drive for press loads, and keep far-end pressure drop under 0.3 bar.
- Log farthest-test-bench pressure during production for a week to prove the sizing in real use.
Dry Air for Windings, Varnish and Insulation
Moisture is the enemy of motor insulation. Copper windings must stay dry before and during varnish impregnation, because moisture trapped in the winding lowers insulation resistance and shortens the life of the motor. The VPI plant is where this matters most: the varnish must cure evenly, and damp air in the plant changes the cure and leaves soft spots in the insulation. The standard that prevents this is a treatment chain, not a single filter: a pre-filter, a refrigerated dryer to a 3 degree C pressure dew point, a coalescing filter to 0.01 micron, and an activated-carbon filter for oil vapour, with a final point-of-use filter at the VPI plant and the winding machines. For air that contacts windings and varnish, an oil-free screw compressor removes the oil risk at source rather than filtering it out.
Oil on a winding is the second risk: it weakens the bond between varnish and copper and shows up as a failed insulation test. Keep the compressor intake away from the stamping hall so the machine does not breathe oil mist, fit a heavy-duty intake pre-filter, and check it weekly in the first months. Drain condensate with automatic zero-loss drains, slope lines to drain legs, and test the air at the VPI plant quarterly for oil, moisture and particles. Change coalescing elements on pressure drop, not on a calendar guess, because a clogged element is the most common cause of a slow pressure sag at the winding machines.
- Fit pre-filter, refrigerated dryer, 0.01 micron coalescing filter and carbon filter, with a final filter at the VPI plant.
- Consider an oil-free screw compressor for winding and VPI, where air contacts copper and varnish directly.
- Keep the compressor intake away from stamping oil mist, and test VPI-plant air quarterly.
Buying from China: Sizing Sheet for a Motor Plant Compressor
QiAir is a Chinese manufacturer and supplier of screw air compressors, and a motor order should start with a sizing sheet that names the press count. Send the supplier the number of stamping presses, winding machines, VPI plants and test benches, the coincident peak at 6 to 7 bar, the air-quality standard the VPI plant requires, ambient temperature and humidity, and the distance to the farthest test bench. Ask for a quotation that states the dryer type and filtration grades explicitly, and ask whether an oil-free machine or a filtered oil-injected machine fits the winding specification better, with the cost and maintenance difference spelled out.
Agree the acceptance test before shipment: a full-load run at rated pressure, a dew point reading at the dryer outlet, and an oil-aerosol check at the final filter outlet. On arrival, install on a level plinth with clear cooler airflow, connect drains before the first run, and survey pressure at the farthest test bench during the first full production week. Keep a log of pressure, dew point and filter changes, and review it monthly, because a slow rise in dew point is the earliest sign that a dryer needs attention before motors start failing their insulation tests.
- Send the supplier press, winding, VPI and test-bench counts, coincident peak and farthest-bench distance.
- Ask for dryer type and filtration grades in writing, and compare oil-free against filtered oil-injected on total cost.
- Accept on a full-load test plus dew point and oil-aerosol checks, then survey pressure at the farthest test bench in week one.
Frequently asked questions
What pressure does a motor and generator factory need?
A motor and generator factory needs clean, dry air at 6 to 7 bar for lamination stamping, winding, varnish impregnation, rotor balancing, assembly and test benches. Keep far-end pressure drop under 0.3 bar, because a pressure dip at the balancing machine changes the reading, and size on the coincident peak of stamping, winding and VPI cycling.
Why must motor winding air be dry and oil-free?
Moisture trapped in a winding lowers insulation resistance and shortens motor life, and oil on copper weakens the bond between varnish and winding. A pre-filter, refrigerated dryer to a 3 degree C pressure dew point, 0.01 micron coalescing filter and carbon filter in series protect winding and VPI, and an oil-free screw compressor removes the oil risk at source.
What size screw compressor does a motor factory need?
A mid-size motor plant with four to twelve stamping presses, six to twenty winding machines, a VPI plant and two to four test benches typically needs 4 to 10 cubic metres per minute at 6 to 7 bar, roughly a 30 to 75 kW screw compressor with a variable speed drive. Add a 500 to 1000 litre receiver per 10 cubic metres per minute, and verify pressure at the farthest test bench under full load.
Related reading
- Screw Compressor Heat Recovery: Turning Waste Heat into Factory Savings
- IoT Monitoring for Screw Compressor Rooms: A China Supplier's Practical Setup
QiAir is a Chinese manufacturer and supplier of screw air compressors. If you are sourcing a screw compressor from China — for a factory, a food plant, a construction site or a new production line — contact QiAir for a sized quotation, documented performance data and export support.